Challenge: Three city blocks; 20 ft. depths; utility conflicts; Granular sands.
Solution: Block by block staging; trench box technology; experienced crew; City of Charlevoix Assistance.
Spring and early summer 2015 saw Team Elmer's working in downtown Charlevoix, where an MDOT project called for a major project on a key city street. The project demanded the replacement of water and sewer lines for a three-block stretch of the city's State Street. While the work didn't put Team Elmer's on Bridge Street -- Charlevoix's busy main drag - it did place is just one block over on another busy road.
The location of the project brought the first challenge: with Team Elmer's setting up shop on State Street for the start of Charlevoix's busy summer season. We had to figure out a way to do the work with minimal interr... Read more
Spring and early summer 2015 saw Team Elmer's working in downtown Charlevoix, where an MDOT project called for a major project on a key city street. The project demanded the replacement of water and sewer lines for a three-block stretch of the city's State Street. While the work didn't put Team Elmer's on Bridge Street -- Charlevoix's busy main drag - it did place is just one block over on another busy road.
The location of the project brought the first challenge: with Team Elmer's setting up shop on State Street for the start of Charlevoix's busy summer season. We had to figure out a way to do the work with minimal interruption to the surrounding town. State Street may not house as many restaurants or tourist shops as Bridge Street, but it does house City Hall, the county building, and the fire department. It was essential for Team Elmer's to keep these high-profile buildings accessible during the project's three-month schedule.
The solution to that particular hurdle was to perform the project in stages. Rather than excavating the entire road from one end to the other, Team Elmer's went block by block, removing asphalt, curb, gutter, and existing pipe and sewer structures. This division of the project allowed other segments and buildings along the road to remain open and accessible while crews continued to work.
The main hurdle of the project wasn't the summer crowds, though. Rather, the biggest challenge Team Elmer's faced on the particular job was the depth of the excavation. Charlevoix's existing sanitary sewer and water main systems were extremely deep in the ground -- even reaching depths of 20 feet in some spots. The City of Charlevoix wanted construction compatibility with the existing system, requiring Team Elmer's to keep the new installations 20 feet down as well.
The depth of the removals and installations created extra risks that wouldn't be presented in a standard four or five-foot deep water and sewer project. In particular, Team Elmer's kept running into utility conflicts and even had to redesign certain parts of the project in the field in order to circumvent those conflicts. Luckily the City of Charlevoix and a few local subcontractors were able to lend a hand, warn our team about certain obstacles and provide helpful advice to keep the project rolling past challenges.
Date Started: April 2015
Date Completed: July 2015
Self Performed: 73%
Partners: Payne & Dolan, J. Ranck Electric, Ryan Brother
1.800.3ELMERS
231.943.3443
231.943.8975 Fax
P.O. Box 6150
3600 Rennie School Rd.
Traverse City, MI 49685