Garland Street

DJI 0004 1 cFWExhU

Project Overview

Challenge: Installing Detailed Stamped Concrete For Sidewalk and Roadway; Field Adjustments To Unknown Underground Utilities

Solution: Patience, Attention To Detail; In-House Manhole Manufacturing And Invert Adjustment For Field Changes

As the City of Traverse City works to revitalize the downtown Warehouse District, Team Elmer's is one partner helping lead the charge. In the spring of 2016, we completed the Pine Street pedestrian bridge built across the Boardman River, with the goal of connecting the Warehouse District to the rest of downtown Traverse City in meaningful way. Previously, the Warehouse District had been isolated from downtown, but Team Elmer's helped to close the separation.

With the gap between the Warehouse District and the rest of downtown successfully bridged—both literally and figuratively—Team Elmer's set to work on the next st... Read more

Project Details

CLIENT
City of Traverse City
LOCATION
Warehouse District, Downtown Traverse City
DESIGN ENGINEER
Timothy Lodge, City of Traverse City Engineering Department
CONTRACT
1,581,707