Butch's Tackle Soil Excavation

butchsfinished

Project Overview

Challenge: Confined site, existing structures, contaminated soils removal, and accelerated schedule off-season

Solution: Off-site staging, pre-planning, micropile installation, and all-season work force

As part of a complete soil remediation project, Team Elmer's removed more than 15,000 tons of contaminated dirt from Butch's Tackle and Marina in Bellaire.

Releases from an underground fuel storage tank contaminated soils and groundwater near the outlet of the Clam River into Torch Lake. Storage tanks had been removed years ago, but the contaminated soils and groundwater remained at the site, much of it beneath a county road. The close proximity of homes, garages, and Butch’s Tackle prevented conventional dig and haul work to remove the contaminated soils.

A system of micro piles was implemented to support the buil... Read more

Project Details

CLIENT
MDNRE
DESIGN ENGINEER
AECOM
CONTRACT
2,274,454

Click image to view larger

 