e-News: Tue Jan 05 2010

Year-End Wrap Up

The Biggest, The Best and The Strangest of 2009...


It's the first week of 2010, so we're taking one last look at the past year, and sharing some 'award-winning' projects we tackled with our valued customers and partners. Read on to hear more about some incredible achievements, teamwork and fabulous feats!


Our Biggest Milestone

Owner: Michigan Department of Transportation
Details: While working on the new bridge deck project on M-22, Elmer's Concrete poured its one-millionth yard of concrete in Traverse City!



Most Unique Project
Owner: King's Challenge Golf Course
Details: We pulverized and repaved the existing 8-foot wide cart paths, all while tiptoeing along the greens. We also rebuilt the tee box areas and changed the grades on the fairways. It was very nimble work for such heavy machinery!



Biggest Hole Filled
Owner: ITC Power

Contractor: Total Foundations
Details: We poured 90 yards of concrete into a large caisson "hole" for the Power Line Tower Foundation in Croton near the Newaygo-Freemont area. The trucks poured their contents in less than five minutes each to fill this crater.



Deepest Hole Dug with an Excavator
Owners: Lake County Road Commission & Conservation Resource Alliance
Engineer: Wade Trim

Details: We went digging 28 feet under Silver Creek River in Luther near Cadillac to set the foundation for an improved bridge box culvert and road crossing.

 The project as a whole helped preserve the trout and other wildlife in Silver Creek.

Deepest Hole Dug with Scrapers & Largest Amount of Dirt Moved the Fastest
Owner: Wexford County Landfill

Details: Not only digging 60 feet with scrapers, but also moving 107,203 cubic yards of material in a mere 15 days was required to create this new landfill cell.
 Get a load of this: 100,000 yards of material covers a football field almost six stories high!




Largest Amount of Dirt Moved

Owner: Ottawa County Farms

Details: Elmer's moved 390,698 cubic yards of material near Coopersville to create new landfill cells.

 That's a football field almost 24 stories high!


Catch-Up Award & The Greenest Project

Owner: GTB Turtle Creek Casino & Hotel
Construction Manager: R. Clarke Associates
Details: To ensure the least amount of impact to casino goers, the parking lot reconstruction and entrance relocation project started two weeks late and finished one week early. To save time, money and the environment, 10,000 yards of pulverized asphalt were recycled and used during this project.

Shakiest & Most Unusual Sprayroq Project

Owner: The City of Manistee

Engineer: Abonmarche

Details: A 54-inch diameter brick storm water discharge structure was installed 20 feet below grade in the early 1900s on a path that runs under the railroad tracks and to the river. A sink hole developed next to the tracks from brick deterioration in the tunnel system. Elmer's replaced missing brick and coated it with Sprayroq to reinforce the structural integrity of the system. When the trains went speeding overhead, there was a whole lot of shaking going on!





Tallest Crane Lift

Owner: American Tower

Contractor: Cell Air

Details: Our crane lifted a cell tower 285 feet in St. Helen. We even notice better reception from here.





Busiest Project of the Year
- It's a three-way tie!



Owner: Traverse City Area Public Schools

Engineer: Gosling Czubak
Details: The West Middle School parking lots were completely redesigned for better traffic flow, which required eight weeks of multiple crew construction to finish the project on schedule.

Owner: Glen's Market-Manistee
Contractor: Rohde Construction
Details: We used our creativity to transfer fill dirt across the road via a conveyor system. Due to sharp temperature declines, retaining wall builders lifted and placed two million pounds of versa-loc block to help the team stay warm!

Owner: GTB Turtle Creek Casino & Hotel
Construction Manager: R Clarke Associates

Details: Some of the weeks during this project had five separate crews working on various sections at the same time.


Congratulations everyone and may your New Year be doubly productive!
 

Home Office:
 

1.800.3ELMERS
231.943.3443
231.943.8975  Fax

P.O. Box 6150
3600 Rennie School Rd.
Traverse City, MI   49685