Challenge: Handling a massive amount of work (approximately 38,000 labor hours) on an extremely compressed schedule; adhering to strict and demanding specification standards; working in temperatures ranging from 20 to 98 degrees Fahrenheit, due to the 24/7 work schedule
Solution: Breaking the schedule into phases to make the project seem less daunting; recognizing the high stakes of adhering to spec standards; using different technology, crews, and an “all hands on deck” mentality to keep the work site running around the clock
The East-West Runway 10/28 at Cherry Capital Airport in Traverse City, Michigan dates back to a time when airports across the country were building shorter runways. At 6,500 feet, it was a bit too short for large commercial jets to take off with full capacity flights. The problem was especially pressing in the summertime, thanks to the heat and density of the air. Hotter air is less dense, which means airplanes need more runway length to take off. The only quick-fix option to get flights into the air safely was to reduce their weight, so the airport was consistently displacing up to 14 passengers per flight in the summertime – thi... Read more
The East-West Runway 10/28 at Cherry Capital Airport in Traverse City, Michigan dates back to a time when airports across the country were building shorter runways. At 6,500 feet, it was a bit too short for large commercial jets to take off with full capacity flights. The problem was especially pressing in the summertime, thanks to the heat and density of the air. Hotter air is less dense, which means airplanes need more runway length to take off. The only quick-fix option to get flights into the air safely was to reduce their weight, so the airport was consistently displacing up to 14 passengers per flight in the summertime – this added up to years of lost revenue.
After decades of planning, Cherry Capital Airport had to decide on a solution. In order for runway 10/28 to provide enough length for capacity jets to take off in the heat of summer, it needed to be over 7,000 feet long.
The first strides of the runway expansion project took place back in 2013, when Cherry Capital Airport added 400 feet to the east end of the 10/28 runway. However, the airport needed another 115 feet to meet the 7,000 feet requirement. That’s where Team Elmer’s comes in.
Challenges
One of the biggest challenges of this project was the tight deadline. Team Elmer’s had to complete six months of work in three months, and only had a 14-day window to work on the east/west runway while it was closed. This led to the vast majority of the work being completed in 30 days.
To get all of the work done in such a short period of time, crews worked 24/7 with carefully coordinated shift changes. To keep a tight schedule, the project manager had to break it down to the minute to make sure everything kept running smoothly – communication and implementation really were the keys to this project.
Other challenges included:
Solutions
Team Elmer’s rose to the challenge, created solutions, and added value for the project owner:
Technologies & Specifications
With the Cherry Capital Airport project came new technologies. Team Elmer’s implemented new automated machine guidance, as well as specialized gravel and asphalt.
P-209 — Also known as 21AA on steroids. P-209 is a 100% dense grade aggregate that is specified to hold up to the wear and tear of airport traffic. The FAA tested on grade every 800 tons with a 0” to ½” grade tolerance. Compared with MDOT testing of every 1,000 tons in a stockpile, P-209 comes with a more stringent standard than the usual materials Team Elmer’s uses. P-209 requires 100% modified proctor density, which meant Team Elmer’s had to have plenty of water handy with the extreme temperatures. 21AA has a 98% standard proctor from MDOT —another example of the increased standard that comes with P-209.
P-401 & P-403 — A specialized asphalt mix used for airplane runways and designed for each airport based on airplane weights and flight frequency. The FAA requires an AASHTO accredited lab to produce the mix design and with the labs being limited nationwide, the process of producing P-401/403 mix design formula is about a 10-week process.
The testing requirements are rigorous for P-401/403– testing every 500 tons with a minimum of four tests every time you produce material. One day of paving required 16 full sets of tests, equaling about 32 hours of testing. Penalty of not meeting the specifications were to completely remove and replace the failed section, the pressure was on. Team Elmer’s was vigilant and completed the project without any failures.
Automated Machine Guidance — To ensure Team Elmer’s met the FAA grade tolerances, they used automated machine guidance for milling and paving for the first time. The mill tapered from 2” cut to 0” cut with a 4/100th tolerance. By using a 3-dimensional tin loaded into global positioning system satellites or total robotic stations on-site, Team Elmer’s was able to ensure that all milled surfaces removed the exact amount of material to meet future elevations(think more material removed in a high spot and less material removed from a dip in the runway). This 3-D milling and paving process was able to maintain elevations during the 115 foot addition, 800 foot reconstruction, and over 7,000 foot resurfacing.
Despite the challenges and careful planning, Team Elmer’s got lucky: Inclement weather stayed out of sight. With no weather delays, Team Elmer’s was able to get the job done—a Herculean feat given the extremely condensed schedule. The new 115-foot runway section wasn’t the full extent of the work, either. Other highlights of the job included resurfacing all 7,015 feet of the runway (equivalent to 18 car lanes on a mile-long stretch of highway), plus a full removal and reconstruction of an abandoned intersecting 800-foot runway portion. Now, even passengers will be able to notice and appreciate the finished product—whether in the form of smoother landings or fewer displacements on summer flights.
Date Started: August 5, 2017
Date Completed: Spring 2018, MAJORITY OF WORK COMPLETED IN 30 DAYS
Self-performed: 70%
Partners: J Ranck Electric, PK Contracting, Action Traffic Maintenance, Carnal International Grinding and Grooving, North Slope, GEAB, Soils and Structures, Inland Seas, and GFA
1.800.3ELMERS
231.943.3443
231.943.8975 Fax
P.O. Box 6150
3600 Rennie School Rd.
Traverse City, MI 49685